Operation 1: Tire Work Overview
Ground Course
Three Tire Turn
Pounding Tires
Basic step-by-step to pound a tire:
What size tires to use where?
Tire Pounding Tricks of the Trade. Squishy Tire
For spaces too small for a “Squishy Tire”
Shovel Trick for Increasing Height of Pounded Tires
Pick Trick for increasing height of pounded tires
Thermal Wrap
Steps to install the thermal wrap:
Install the thermal wrap
Vent Tubes
Steps to install the vent tubes:
Install the vent tubes
Cistern Installation
Steps to install the cisterns:
Install the Cisterns. STEP ONE - Make the compacted level pad for cistern placement
STEP TWO - Place the cisterns
STEP THREE - Plumb the cisterns
STEP FOUR - Insulate the top of the cisterns
STEP FIVE - Gently bury the cisterns
Front Stem Wall
Step 1 - Locate the stem wall
Step 2 - Layout first course
Step 3 - Layout second course
Step 4 - End caps
End caps
Resources. Staging List for Operation One: Tire Work
Glossary of Terms
Operation Two: Concrete Work
Отрывок из книги
Operation One defines the overall footprint of the building. For a two bedroom Earthship, 20 people can stay busy and accomplish more, taking advantage of the “group effort”.
As with any construction project, there are many things going on at once. This book is meant to be a step by step guide, therefore, it is important to follow these directions and proceed accordingly, step-by-step.
.....
•Layout first tire and string.
•Pound first few courses.
.....