Читать книгу IT Architecture from A to Z: Theoretical basis. First Edition - Vadim Aldzhanov - Страница 46
PROJECT MANAGEMENT METHODS AND TECHNIQUES
Earned Value Analysis (EVA)
ОглавлениеEarned Value Analysis (EVA) is the calculation of project performance indicators within the scope of the acquired volume. EVA is based on the same principles as cost trend analysis and is usually used in large projects. The basis is taken from the figures: The earned value, planned and actual costs. Let’s consider the following example:
The task 1 must be completed by one performer (P1) within two days (2 x 8 hours = 16 hours), the cost of work of the performer is $ 10.00 per hour (planned expenditure = $ 10.00 x 16 hours = $ 160.00).
In fact, the performer finished work on the third day, having spent additional two hours. The indicators are the fact of time (2 x 8 hours +2 hours = 18 hours), while actual expenses = $ 10.00 x 18 hours = $ 180.00.
The result is:
On the morning of the third day the result of the task 1 = 16 / (16 +2) * 100% = 89% and the cost of the Task 1 = $ 180.00
Conclusion: Common sense tells us that we spend money faster than we get the result.
Main method indicators:
Planned Value (PV) is an amount of planned work within basic prices. In our example, PV is equal to $ 160, since the basic amount of work to be completed by Wednesday is 16 person-hours, and the base price is $ 10 per hour.
Earned Value (EV) is a completed part of the work of the planned amount. It is percentage of completion of work, multiplied by the base task budget. This indicator used to be called BCWP (base cost of work performed). In our example, EV is equal to $ 142, since the percentage of the task carried out is equal to 89%, and its base budget is $ 160.
Actual Cost (AC) is a real cost of work performed. It is measured by the amount of money that is actually available for the work performed. In our example, AC is equal to $ 160, because in fact, the performer spent 16 hours, and every hour costs $ 10.
Budget at Completion (BAC) is fixed at the start of the project as the amount of the approved budget for the entire project. In our case, it is equal to $ 160.
Cost Variance (CV) is a value deviation (formula: CV = EV-AC). $142.00 – $160.00 = – $18.00. Negative value means that the budget has been exceeded, while a positive implies that the budget has been saved. In our case, the budget has been overspent.
Schedule Variance (SV) is a time deviation (formula: SV = EV-PV). $142.00 – $160.00 = – $18.00. Negative value means that estimated deadlines are due, while positive one means that the deadlines have been outpaced. We are behind schedule.
Cost Performance Index (CPI) is a cost performance index (formula: CPI = EV / AC). If the index is greater than 1 the budget is saved, if it is less than 1, the budget has been exceeded. In our case, $142.00 / $160.00 = 0.89. The budget over expenditure is 11%.
Schedule Performance Index (SPI) is a deadline index (formula: SPI = EV / PV). If the index is more than 1 the schedule is overtaken, if it is less than 1, the base schedule is outpaced. In our case: SPI = $142.00/$160.00 = 0,89. The schedule is 11% outpaced.
Estimate at Completion (EAC) represents the expected total cost of the project after the completion of the remaining work (Formula: EAC = BAC / CPI). In our case: $160.00 / 0.89 = $180.00. The current estimated cost of the project task is $ 180.00.
Estimate to Complete (ETC) calculates how much more money is required to complete a project (Formula: ETC = EAC-AC). In our case: ETC = EAC-AC = $180.00 – $160.00 = $20.00 are still required to complete the task.
Variance at Completion (VAC) indicates expectations for cost over expenditure or budget savings (formula: VAC = BAC-EAC). In our case: VAC = BAC-EAC = $160.00 – $180.00 = – $20.00. The budget over expenditure is $20.
Formulas for calculating the project status: EAC = AC + Button-up ETC, EAC = AC + BAC – EV, EAC = BAC / Cumulative CPI, EAC = AC + [(BAC – EV) / Cumulative CPI x Cumulative SPI], EMV = probability x impact, EV = BAC /% of completion, TCPI = (BAC – EV) / (BAC – AC).