3.8.4 Red-Line Drawings Left Too Late

Оглавление

If the Construction Department does not complete the Red-Line Drawings in an orderly or timely fashion, then there is a very real risk that the commissioning activities will not be allowed to commence on time due to the lateness of the As-Built Drawings that the Engineering Department is required to produce. This problem is exacerbated in the situation where the Field Engineering work (particularly incorporation of the contents of the Red-Line Drawings) is not done on the Site but, instead, is conducted at the Contractor's Home Office. This problem is made even worse if that Home Office is in an overseas location compared to the location of the Site.