3.1.4 Meetings with Contractors and Suppliers
ОглавлениеThe design team will meet with contractors and system suppliers often to clarify design issues that are not easily addressed in other forums. During the early phase of the contract, design engineers should schedule monthly meetings with the system integrator. Later meetings should include electrical contractors; heating, ventilation, and air-conditioning (HVAC) contractors; and other subcontractors for coordination purposes.