V. Step 5: Calculate Delay
ОглавлениеOnce entitlement is established, the claimant can work on the delay analysis, if applicable. Contract claims often have a delay component, which results in delay damages. In order to establish that an issue or dispute had a critical impact on the claimant's work, the claimant should use one or more of the four accepted forensic scheduling techniques:
1 time impact analysis;
2 windows analysis;
3 collapsed as-built analysis;
4 as-planned vs. as-built analysis.
The selection of the forensic technique depends on the information available to the claimant and whether the claimant seeks to prove an excusable and compensable delay or an excusable non-compensable delay.