Читать книгу IT Architecture from A to Z: Theoretical basis. First Edition - Vadim Aldzhanov - Страница 36

PROJECT MANAGEMENT INSTITUTE (PMI)
Planning

Оглавление

Defines and clarifies goals and action plans required to achieve the objectives and content of the project. Planning is the definition of clear and precise tasks, and as a result of assignments that serve to achieve the ultimate goal. The goal may be a solution to a problem or the attainment of a state or condition different from the existing one. At this stage, the team decides how they will achieve the goal set at the previous stage. At this stage, the team clarifies and details the goals and project results, as well as the scope of work needed. This information is used to make a calendar plan and estimate the budget, assess the risks and identify the stakeholders. Project planning may require a significant investment of time, effort and resources, depending on its size. As practice shows that efforts and resources can be wasted if you do not plan properly for a specific project before deciding whether to implement it or not.

Project organization is a primary project management task. A project owner, a person or group authorizes to make decisions, should be defined, a project manager should be appointed and a project team should be formed, project managing and interacting procedure should be determined, and the relevant powers to the project manager and project team should be highlighted. Project management beyond the functional boundaries of the organization is one of the project manager’s tasks. He/she has to communicate, generate ideas, negotiate, solve problems and resolve conflicts outside the functional and sometimes geographical boundaries of the organization. Setting a task, justifying the need for a project and describing its capabilities allow formulating the goal of the project. Such a formulation can be very brief, but it should be precise. Setting project objectives is important for two reasons:

• The task clearly defines what needs to be done to achieve the goals;

• A task is an event with determinable deadline.

The “SMART” method helps formulate the project goals and objectives as:

• Specific – be accurate when setting goals;

• Measurable – Set measurable status indicators;

• Assignable – be able to assign a task to someone;

• Realistic – Determine whether the project can actually be terminated duly and within allocated resources;

• Time related – determine the timeframe, i.e. the duration of project implementation.

To achieve this goal, one should perform several basic project tasks. These tasks are private goals and the main project components (sometimes the term “milestone” is used). Individual goals are not actual assignments within the project, but are checkpoints setting the direction of work. They are more precisely formulated than the main goal and action oriented. To achieve the main goal requires realizing all private goals. The allocation of resources for the project implies that money is not the only resource required. The main resources are:

• Financial resources (direct funds required for project implementation and project management);

• Human resources (who, when, how and how long is involved in the project);

• Material resources (available, required, and so on);

• Administrative resources (authorities, organization).

Besides, this list of required resources may include changes in the company’s organizational structure, office space (for large projects), and so on. The practice shows that two most likely scenarios for resource allocation can be identified as follows:

• The project manager determines the necessary resources based on a preliminary plan, which provides an initial estimate of the amount of resources required for the project. The project manager will be able to formulate resource requirements and discuss them with the authorized manager. This scenario is the most preferable one.

• Required resources are assigned without involving the project manager. The project manager usually may not have a choice, regardless of whether sufficient resources are allocated to the project, or not. One should not be misled by the leadership and agree to the level of support, which is clearly insufficient for the project implementation. Caution and common sense should be decisive at this early stage.

The document containing the project review is compiled, analyzed by experts, and then submitted to the organization’s leadership. The next important aspect of project management is the process of splitting a project into parts, resulted in a work breakdown. A work breakdown is a hierarchical representation of a project. It helps the project manager determine the tasks to be done in order to start and finish the project. At this stage, the manager has a goal and a number of tasks that must be expressed through the tasks and work to be performed. A well-defined assignment has the following features:

• Its status and termination date is easy to determine, it has a clearly defined beginning and an end;

• It is clear, since it might have been carried out before. The time and associated costs required for its implementation can be easily estimated using the experience gained during implementation of similar tasks in the past;

• It includes controllable jobs that do not depend on activities comprising other tasks;

• It is typically one continuous work sequence.

The time to complete each task within the project should be estimated. The time required to complete the task is a random value. Therefore, if this task is recurrent, the time will change for many times. This will be fair even for regular tasks. This variation is caused by the following factors:

• The qualifications level of employees involved;

• Using various equipment;

• Availability of materials;

• Force majeure (diseases, natural disasters, accidents, rotation, etc.)

Such events may occur, but it is impossible to predict them when implementing a specific project or a task. However, they should be taken into consideration. To do this, one can use the critical path evaluation method.The cost of each assignment should be also estimated. There are four main cost categories (although organization’s chart of accounts may be used) to determine for each assignment:

• Work force;

• Materials;

• Other direct costs (business trips, telephone, contractual services);

• Indirect costs (overhead).

The next step is to determine the sequence of assignments within the project. The assignments of simple projects may be carried out one by one. Another way is to analyze all the assignments and determine which ones are to be completed before starting the others. Such an analysis reveals the order in which several assignments can be carries out simultaneously. The critical path method (MCP) determines the sequence of simultaneous assignments that allows completing a project in a timely manner. Identifying critical assignments, determining the critical path and constructing a priority diagram is to provide graphical presentation of the project. This requires mastering a few simple charting rules. An assignment is the main ordered “unit of analysis”. Tasks are represented on the diagram as rectangles, called “assignment nodes”. The symbols depicted in the rectangle describe the temporary assignment properties. Some of them describe the assignment characteristics (for example, the assignment number), while others are assignment associated estimates (ES, EF, LS, LF). The project time is the longest time path in the diagram. The longest sequence of assignments is called the critical path. As long as the assignments within the critical path are completed duly, the project is within the schedule. The four calculated parameters (ES, LS, EF, and LF) for each assignment node are to be determined. The following calculated values will be used to determine the project time and the critical path:

Early start (ES) is the earliest point in time when all the previous assignments have been completed and this assignment can be started. The ES for the first assignment is time period 0.

Early finish (EF) is the ES time plus the estimated time to complete the assignment. The ES time for an assignment preceded by one task is the EF time for this previous task. The ES time for assignments that are preceded by two or more assignments is the longest EF time for these previous assignments.

Late start (LS) and Late Finish (LF) are the latest points in time when the assignment can be started (LS) or finished (LF) without increasing the time to terminate the entire project.

To estimate these points, one should move the Backward Pass. First, the LF time for the last assignment in the diagram is taken as the EF time of the assignment considered. The LS time for a given assignment is equal to its LF time minus the estimated time to complete this assignment. The LF time for all preceding assignments is the shortest LS time for all assignments for which the assignment considered is preceding. It is necessary to calculate one more value, called the time reserve for the assignment.

Time reserve is an allowable value of delay in the start or finish of the assignment, which does not cause a delay when carrying out the entire project. The time reserve is a mathematical difference LS – ES (or LF – EF). The definition of a critical path is a sequence of assignments having a zero reserve.

Terms of reference is a transition from the planning (definition, drawing up a plan) to the implementation (organization, control, termination). As shown later, the terms of reference is the foundation for internal consistency of the project providing the basis for all administrative decisions. Let’s consider the terms of reference, paying focusing on its parts and their use as controls. The terms of reference of the project is to receive:

• A description of the challenge, the general approach to solve it and the expected benefits resulting from it;

• Full description of the project assignment, time and resources required;

• A detailed description is required for the administration to decide whether to proceed to the stages of the project;

• A dynamic tool for the project manager and the project team to be used for decision making throughout the project;

• Reference documentation for administrative control;

• A means to familiarize new members of the project team with the project and prepare for its implementation;

• A report for representatives of your organization who are not involved in the project directly, but should be aware of it.

An assignment is an obvious key document in the project. The terms of reference should be understandably written and used by the leadership, the project managers, the members of the project team, and other managers, as well as specialists who need this information. The terms of reference consists of:

• Project name;

• Project objectives;

• Project Manager;

• Project owner or stakeholders;

• Project team.

• Assignments consist of three subsections: the number, a short but meaningful title, and a description. It should contain specific statement activities to be carried out.

• Estimated start and termination dates;

• Project implementation schedule;

• Project estimate summarized at the assignment level;

• Metrics and criteria for achieving goals;

• Additional terms.

All projects involving financial aspects of profit may require a thorough assessment of the project impact on income and expenses, before the project is approved.

Schedule and progress is a chart indicating the start and finish dates and the planned duration for each work package. This schedule and progress is usually depicted as a Gantt chart and network graphs specifying the logical sequence of the execution of work packages. The planning process group includes the following processes:

• Developing a project management plan;

• Content management plan;

• Collecting requirements;

• Definition of content;

• Creating a hierarchical operational structure;

• Developing a schedule management plan;

• Definition of operations;

• Determining the sequence of operations;

• Evaluation of operational resource;

• Estimation of the operational duration;

• Scheduling;

• Developing a cost management plan;

• Estimating;

• Budgeting;

• Quality planning;

• Development of a human resources management plan;

• Communication planning;

• Risk management planning;

• Risk identification;

• Qualitative risk analysis;

• Quantitative risk analysis;

• Risk response planning;

• Procurement planning;

• Development of a stakeholder management plan.

IT Architecture from A to Z: Theoretical basis. First Edition

Подняться наверх