1.4 Common Elements for Construction Projects

Оглавление

Construction work is ever present amongst us, whichever direction you care to look, taking on many different forms. Construction activities range from major city redevelopments to petrochemical plants, and with so many things in between; the list of possible construction work seems endless. And the Construction Industry is simply huge. For infrastructure work alone, according to McKinsey & Company the value anticipated to be undertaken worldwide over the period 2018–2023 is in the order of USD 77 trillion.14

There are many steps that need to be taken first before even one spade can strike the ground in earnest to commence the physical on-site work for a major Project. For most Projects, a feasibility study will need to be conducted before the Employer will be prepared to commit the necessary resources to proceeding with the implementation activities. A typical feasibility study will address the questions of the legality of the proposed Project and whether its construction would be technically feasible, as well as being fully justified on economic grounds. It is not usual for a Contractor to be involved in ascertaining the viability and feasibility of a Project unless the Contractor is required to be involved in organising and/or providing the finances. This requirement can sometimes be necessary under an EPC Contract if payment to the Contractor is not due to be made until a number of years after the facility has been operating. It is most certainly required in Projects where the Build-Operate-Transfer (BOT) concept is employed.15 BOT Projects may also be implemented under an EPC arrangement. The problems for some Projects can start with an inadequate feasibility study, which can then lead to severe cash flow problems for the Employer (and, ultimately, the Contractor). To avoid the possibly disastrous problems that an inadequate feasibility study can cause, it has been proposed by some (see Hyari and Kandil) that a series of peer reviews should be conducted of all feasibility study material.16

There are many different ways for an Employer who wants to have construction work carried out to arrange for the appointment of a Contractor to do the work. However, whether the work is let under a Traditional Contracting arrangement or an EPC/Design-Build arrangement, the Contractor's work will almost certainly involve both procurement and installation/construction work. It will therefore be of no surprise that a great deal of what I have written will quite obviously also apply equally well to non-EPC/Design-Build Contractors, despite the intended focus of this book being on EPC/Design-Build Projects.

Whether or not a Project is conducted under an EPC or Design-Build arrangement, failure to manage the implementation risks properly for a major Project can lead not only to huge financial losses but also to bankruptcy for the Contractor's entire business. Mismanaging a major Project's risk portfolio should therefore be viewed as a gamble too far for most Contractors, and advance planning is therefore vital. Consequently, no matter what type of contractual arrangement the successful bidder will eventually be working under (whether the Traditional Contracting approach or an EPC/Design-Build route), there are certain basic preparatory bidding steps that need to be taken. The following sets out what those steps are, and which are essential if the bid pricing is to stand a good chance of adequately covering all the costs involved for undertaking all the work necessary to complete the Project successfully:

1 Planning how the work will be done through the development of a comprehensive Work Breakdown Structure (WBS) for the Project. Sometimes the starting point might be an outline WBS required/prepared by the Employer's Team and issued with the Invitation to Bid documentation. No matter, the WBS needs to be worked up into a truly meaningful list of all the work activities/elements involved and, under an EPC or Design-Build Project, the Engineering, Procurement and Construction components should each have their own list of work activities/elements clearly identified under those specific headings.

2 Using the completed WBS, the Contractor must then establish the sequence of undertaking the work activities/elements involved, and also determine the length of time needed to deliver the completed work for the entire Project (the Project Schedule). If it is also possible to establish the labour and construction equipment resources required reasonably accurately, then that would be of great benefit, since it would help to give more confidence in both the anticipated Project completion time and the Contractor's bid pricing. However, that is more often than not very difficult to achieve under an EPC/Design-Build Project, due primarily to the lack of detailed design information available from which to measure the physical work quantities that will be required for the completed Project.

3 Having prepared the WBS and established what the Project Schedule looks like, the Contractor must then conduct a preliminary risk analysis. The aim should be to establish what the major risks are that, if not controlled adequately, would have the potential to cause major problems and thereby stop the Project from being as successful as it could be. Those risks should then be set down in a preliminary Project Main Risks Register, alongside which suitable risk mitigation measures should be included (wherever it is considered possible/feasible to achieve that), aimed at preventing those risks from materialising.

4 The final essential ingredient in submitting a worthwhile, comprehensive bid is for the Contractor to prepare an outline Project Execution Plan (PEP) that incorporates all the findings from the WBS, the Project Schedule and the Project Main Risks Register. A properly prepared and well thought out PEP is, in essence, the storyline for how the Project will be undertaken. If written competently, the PEP would allow the Contractor's Project Implementation Team to form a very clear picture as to what the most effective management set-up ought to be. That too would give the Contractor added confidence about the adequacy of the bid pricing.

All of the above topics, common to all construction Projects (EPC/Design-Build or otherwise), are dealt with in far more detail in the following chapters of this book, along with advice as to (i) what to look out for when compiling the necessary information and documentation, (ii) what things can go wrong, and (iii) how to avoid such problems occurring.