Showing Up Again and Again: Recurring Tasks
ОглавлениеSome tasks occur repeatedly in projects. For example, attending a monthly project debriefing or generating a quarterly project report is considered a recurring task.
No one wants to create all the tasks for the monthly debriefing in a project that will take a year to complete. Instead, you can designate the recurrence, and Project automatically creates the 12 tasks for you.
Here’s how to create a recurring task:
1 Click the Task tab on the Ribbon, click the bottom part of the Task button (with the down arrow) in the Insert group, and then click Recurring Task.Figure 3-5 shows the Recurring Task Information dialog box that will insert a recurring task for a monthly meeting on the 10th of every month. The meeting is scheduled to occur every month from January through July.
2 In the Task Name box, type a name for the task.
3 In the Duration box, click the spinner arrows to set a duration, or type a duration, such as 1d for 1 day.Edit the abbreviation to specify a different time unit, if needed. You can read about the abbreviations that you can use for units of duration — such as h for hours — in Chapter 5.
4 Select a recurrence pattern by selecting the Daily, Weekly, Monthly, or Yearly radio button.The option you select provides different choices for the rest of the recurrence pattern.
5 Depending on the selections offered to you, make choices for the rest of the pattern.For example, if you select the Weekly radio button, you must choose a Recur Every x Week(s) On setting and then choose a day such as Friday. Or, if you select Monthly, you must specify every two months, every three months, and so on. You also need to choose which day of the month the task is to recur.
6 In the Range of Recurrence area, type a date in the Start box; then select and fill in either the End After or End By option.For example, you might start on January 1 and end after 12 occurrences to create a task that occurs every month for a year.
7 Click the OK button to save the recurring task.
If your settings cause a task to fall on a nonworking day (for example, if you choose to meet on the eighth day of every month and the eighth day is a Sunday in one of those months), a dialog box appears, asking you how to handle this situation. You can choose not to create the task, or you can let Project adjust the day to the next working day in that period.
© John Wiley & Sons, Inc.
FIGURE 3-5: The Recurring Task Information dialog box.
To assign resources to a recurring task, you have to assign the resources to the individual recurrences, not to the “summary” recurring task. If you assign resources to the summary recurring task, Project doesn’t calculate the hours of work correctly. I talk about assigning resources to tasks in Chapter 9.