INSTALLATION
Оглавление1 Is your organization sure that there is diversity in the labor pool of the primary and backup sites, such that a wide‐scale event would not simultaneously affect the labor pool of both sites?
2 Do you routinely use or test recovery and resumption arrangements?
3 Are you familiar with National Fire Protection Association (NFPA) 1600 – Standard on Disaster/Emergency Management and Business Continuity Programs, which provides a standardized basis for disaster/emergency management planning and business continuity programs in private and public sectors by providing common program elements, techniques, and processes?
4 Has the owner, working with an engineering professional, developed a Design Intent Document to clearly identify quantifiable requirements?
5 Have you prepared a Basis of Design document that memorializes, in a narrative form, the project intent, future expansion options, types of infrastructure systems to be utilized, applicable codes and standards to be followed, design assumptions, and project team decisions and understandings?
6 Will you be provided the opportunity to update the Basis of Design to reflect changes made during the construction and commissioning process?
7 Are the criteria for testing all systems and outlines of the commissioning process identified and incorporated into the design documents?
8 Have you identified a qualified engineering and design firm to conduct a peer project design review?
9 Have you considered directly hiring the commissioning agent to provide true independence?
10 Have you discussed and agreed to a division of responsibilities between the construction manager and the commissioning agent?
11 Do you plan to hire the ultimate operating staff ahead of the actual turnover to operations so they will benefit from participation in the design, construction, and commissioning of the facility?
12 Have you made a decision on the commissioning agent early enough in the process to allow participation and input on commissioning issues and design review by the selected agent?
13 Is the proper level of fire protection in place?
14 Is the equipment (UPS or generator) being placed in a location prone to flooding or other water damage?
15 Do the generator day tanks or underground fuel tanks meet local environmental rules?
16 Does the battery room have proper ventilation?
17 Has adequate cooling or heating been specified for the UPS, switchgear, or generator room?
18 Are the heating and cooling for the mechanical rooms on the power protection system?
19 Have local noise ordinances been reviewed, and does all the equipment comply with the ordinances?
20 Are the posting and enforcement of no‐smoking bans adequate, specifying, for example, no smoking within 100 feet?
21 Are water detection devices used to alert building management of leak or flooding issues?