3.2.3 Field Tests

Оглавление

Field tests (site acceptance tests) as described further in this manual should be conducted after the new control system has been installed and wired and each instrument has been verified and calibrated. The ISA publishes a useful guide to testing requirements that includes site acceptance testing (SAT), system integration testing (SIT), and factory acceptance testing of automation systems in the process industry (ISA, 2011).