Читать книгу Fundamentals of Construction Claims - William J. McConnell - Страница 56

Sample Notice Letter that Conforms to the AIA A201

Оглавление

Via Certified Mail

April 23, 20__

Owner

Address

Re: Project: Project Name

Subject: Section 15.1.3.1 Notice of Claim

Dear Owner/Initial Decision Maker/Architect,

Pursuant to Section 15.1.3.1 of the AIA A201 General Conditions, Contractor hereby submits a formal Notice of Claim for the additional scope of work identified on the revised architectural plans that Owner issued to Contractor one week ago, on April 23, 20__. Specifically, Drawing A.2.06 indicates approximately 80 additional feet of wall assembly that was not contemplated in the bid set of plans that the Contract Price is based upon. Thus, this scope is outside of the defined Work. Contractor is calculating cost and time impacts associated with this additional work and will issue a formal Claim for an initial decision per Section 15.2 of the A201 soon. If you have any questions or comments, please contact Contractor at your convenience.

Sincerely,

Contractor

Fundamentals of Construction Claims

Подняться наверх