Читать книгу Fundamentals of Construction Claims - William J. McConnell - Страница 59

3. EJCDC C-700 General Conditions

Оглавление

The EJCDC C-700 general conditions do not have a specific notice requirement for claims. Section 12.01.B notes that contractor shall deliver claims to the owner and the engineer no later than 30 days after the start of the event giving rise thereto. Therefore, unlike the AIA A201 and ConsensusDocs 200, the claims process starts with the submission of the claim itself within 30 days of the event giving rise to the claim, such as a rejected change proposal by the engineer. This forces the contractor to assemble claims in an expedited fashion. Below is a sample cover letter that might accompany a Section 12.01.B claim.

Fundamentals of Construction Claims