Sample Notice Letter that Conforms to the ConsensusDocs 200
ОглавлениеVia Certified Mail
April 23, 20__
Owner
Address
Re: Project: Project Name
Subject: Section 8.4 Notice of Claim
Dear Owner,
Pursuant to Section 8.4 of the ConsensusDocs 200 contract, Contractor hereby submits a formal notice of claim for the additional scope of work identified on the revised architectural plans that Owner issued to Contractor one week ago, on April 23, 20__. Specifically, Drawing A.2.06 indicates approximately 80 additional feet of wall assembly that was not contemplated in the bid set of plans that the contract price is based upon. Thus, this scope is outside of the defined Work. Contractor is calculating cost and time impacts associated with this additional work and will issue a formal Claim with supporting documentation within 21 days of this notice of claim. If you have any questions or comments, please contact Contractor at your convenience.
Sincerely,
Contractor