Читать книгу Fundamentals of Construction Claims - William J. McConnell - Страница 62
1. AIA A201 General Conditions
ОглавлениеPer Section 2.2.1 of the AIA A201, prior to commencement of the work, the contractor may issue a written request to the owner for proof of funding for the project. The contractor has no obligation to commence the work until the owner provides such evidence. If commencement of the work is delayed due to this issue, the contract time shall be extended appropriately.